Site directory

The Centre

Who we are, who leads us and how we are governed.

Countries

Energy profiles for every country and region in the world.

Programmes

Advisory practice, initiatives and the frameworks behind them.

Transition

Global and national transition frameworks, explained.

Terminal

The CEII Energy Terminal and the market, power and solar intelligence behind it.

Newsroom

Energy reporting from the CEII Desk, with the Centre’s insights, events and publications.

Data

Documented datasets with sources, units and revision dates.

Power

Nigeria plans new transmission grid to tackle collapses

The Federal Government has approved the development of a new Eastern-Western electricity grid to address chronic transmission infrastructure failures.

By the CEII Desk, from reporting by Punch

Key points

  • Procurement for the Eastern-Western grid project is set to begin following presidential approval.
  • The Minister of Power stated that citizens will experience the benefits within two to three years.
  • A nationwide technical audit is underway to identify specific faults across aging grid assets.

What happened

The Federal Government has given approval to construct a new Eastern-Western electricity grid in a bid to resolve recurring collapses within Nigeria's power network. According to Punch, Minister of Power Joseph Tegbe announced the initiative at an energy conference in Lagos. He noted that the administration is preparing procurement processes for the infrastructure expansion.

Mr Tegbe explained that authorities have initiated a comprehensive technical audit of the country's electricity facilities. The assessment aims to pinpoint exact faults—such as damaged towers, insulators, conductors, or relays—to ensure that capital interventions target the correct equipment rather than general repairs.

Why it matters

The minister attributed vulnerabilities in the transmission network to decades-old infrastructure, noting that some active towers and lines date back to the era of the Electricity Company of Nigeria, preceding the National Electric Power Authority.

According to World Bank figures from 2024, electricity use per person in Nigeria stands at 140.6 kilowatt-hours, compared to a global average of 3708.5 kilowatt-hours, while national electricity access is recorded at 62.5 per cent. Upgrading the grid is critical for industrial stability and expanding reliable supply beyond key commercial corridors like Lagos and Abuja.

What comes next

The nationwide technical audit is scheduled to conclude within the coming weeks. Once completed, the Ministry of Power will use the findings to prioritise targeted interventions, while procurement for the new grid buildout moves forward with tangible results expected in two to three years.

Original reporting

This article draws on the following reports. Read them in full on the publishers’ sites.

Context from CEII

Grids decide whether generation becomes power that homes and businesses can rely on. Generation mix, transmission and distribution losses, and tariffs together shape reliability and the case for investment.

62.5% of people in Nigeria had electricity in 2024

Countries in this story

Written by the CEII Desk, the Centre’s automated newsroom, from the reporting credited above and CEII’s own data. Facts are attributed to their sources; the publishers have not reviewed this article. Spotted an error? Tell our editors.

Check your inbox

We’ve sent a confirmation link. Click it to start receiving the CEII Energy Brief.

Privacy choices

Change these at any time from “Privacy choices” at the foot of every page. See the privacy notice.

Categories