Site directory

The Centre

Who we are, who leads us and how we are governed.

Countries

Energy profiles for every country and region in the world.

Programmes

Advisory practice, initiatives and the frameworks behind them.

Transition

Global and national transition frameworks, explained.

Terminal

The CEII Energy Terminal and the market, power and solar intelligence behind it.

Newsroom

Energy reporting from the CEII Desk, with the Centre’s insights, events and publications.

Data

Documented datasets with sources, units and revision dates.

Gas

US FERC proposes blanket permit system for LNG facilities

The United States Federal Energy Regulatory Commission has introduced a proposed blanket authorisation framework to streamline approvals for liquefied natural gas infrastructure.

By the CEII Desk, from reporting by Offshore Technology

Key points

  • FERC issued a unanimously backed Notice of Proposed Rulemaking for LNG sites.
  • The framework adapts an existing four-decade-old pipeline certificate programme.
  • A three-tiered structure categorises activities by potential impact and notification requirements.
  • Stakeholders have 60 days to submit comments following publication in the Federal Register.

What happened

According to Offshore Technology, the United States Federal Energy Regulatory Commission (FERC) has unveiled a proposed blanket authorisation framework for liquefied natural gas (LNG) projects. Approved unanimously through a Notice of Proposed Rulemaking, the system aims to remove the necessity for individual regulatory orders under specific sections of the Natural Gas Act.

FERC modelled the new initiative on its established blanket certificate programme for interstate natural gas pipelines, which has functioned for approximately forty years. The draft framework introduces a three-tiered system to categorise project activities based on their expected scale and impact.

Project tiers and conditions

Under the proposed rules, minor tasks that maintain current operating conditions and capacity could receive automatic clearance. Other actions that expand plant capacity within existing boundaries would require a sixty-day prior notice to the commission.

A third category involves a ninety-day advance notification period for building entirely new infrastructure, such as storage tanks, liquefaction trains, and marine loading berths. While these projects may extend past current site perimeters, they remain subject to specific location, type, and scale restrictions.

The draft also incorporates standard engineering and environmental conditions to manage potential project impacts and ensure adherence to legal obligations.

What comes next

FERC chairman Laura Swett stated that the initiative supports national energy infrastructure development while maintaining regulatory safeguards. Interested parties are given sixty days following the publication of the Notice of Proposed Rulemaking in the Federal Register to provide feedback before the commission finalises the framework.

Original reporting

This article draws on the following reports. Read them in full on the publishers’ sites.

Context from CEII

Gas is the flexible backbone of many grids and the designated transition fuel in many national plans, from LNG trade to domestic LPG and CNG. Supply security and pricing drive both power reliability and emissions.

21.9% of electricity in the world came from gas in 2024

Countries in this story

Written by the CEII Desk, the Centre’s automated newsroom, from the reporting credited above and CEII’s own data. Facts are attributed to their sources; the publishers have not reviewed this article. Spotted an error? Tell our editors.

Check your inbox

We’ve sent a confirmation link. Click it to start receiving the CEII Energy Brief.

Privacy choices

Change these at any time from “Privacy choices” at the foot of every page. See the privacy notice.

Categories