Site directory

The Centre

Who we are, who leads us and how we are governed.

Countries

Energy profiles for every country and region in the world.

Programmes

Advisory practice, initiatives and the frameworks behind them.

Transition

Global and national transition frameworks, explained.

Terminal

The CEII Energy Terminal and the market, power and solar intelligence behind it.

Newsroom

Energy reporting from the CEII Desk, with the Centre’s insights, events and publications.

Data

Documented datasets with sources, units and revision dates.

Renewables

Ofgem sets date for record Hornsea 3 transmission tender

The UK energy regulator is preparing to launch its largest offshore transmission asset tender to date.

By the CEII Desk, from reporting by Offshore Energy

Key points

  • Ofgem will open the tender for Hornsea 3 transmission assets on October 21.
  • The competition is valued at approximately £3.5 billion.
  • The project connects the 2.9 GW offshore wind farm to the onshore grid.

What happened

According to Offshore Energy, the UK energy regulator Ofgem will initiate a tender round on October 21 for the transmission infrastructure of the Hornsea 3 offshore wind farm. Valued at roughly £3.5 billion, the process represents the largest Offshore Transmission Owner tender conducted so far.

The competition focuses on the transmission assets moving electricity from the 2.9 GW wind farm to the onshore grid. The infrastructure includes two offshore converter stations completed by September 2026, export and onshore cables, and a converter station located in Norfolk.

Project scope and timeline

Situated 120 kilometres off the Norfolk coast, Hornsea 3 will feature 197 turbines of 14 MW capacity each, supplied by Siemens Gamesa. Foundation installation commenced earlier in the year, with inter-array cable laying slated to begin in October. Commercial operation is anticipated in 2027.

This new round follows Ofgem's previous tender covering assets for East Anglia Three, Inch Cape and Dogger Bank C, which had a combined value matching the single Hornsea 3 project estimate.

Original reporting

This article draws on the following reports. Read them in full on the publishers’ sites.

Context from CEII

Renewables are the fastest-growing part of the world’s energy system. The COP28 goal is to triple capacity by 2030, and solar mini-grids are the fastest route to power for millions of people without electricity.

27.8% of electricity in the world was renewable in 2021

Countries in this story

Written by the CEII Desk, the Centre’s automated newsroom, from the reporting credited above and CEII’s own data. Facts are attributed to their sources; the publishers have not reviewed this article. Spotted an error? Tell our editors.

Check your inbox

We’ve sent a confirmation link. Click it to start receiving the CEII Energy Brief.

Privacy choices

Change these at any time from “Privacy choices” at the foot of every page. See the privacy notice.

Categories